CLM-2025-0215

Approved

Storm damage to stored materials at Elk Grove warehouse site. Unsecured lumber and drywall inventory damaged by wind and rain during November atmospheric river.

$12,400

total incurred

Date of Loss

Nov 20, 2025

Date Filed

Nov 21, 2025

Policy

Inland Marine / Builders Risk

IM-2025-004321

Loss Type

Inland Marine — Weather Damage

Financial Summary

Total Incurred$12,400
Deductible$2,500
Amount Paid$9,900
Open Reserve$0
80% paid$2,500 remaining

Location of Loss

Pacific Ridge Warehouse, 9100 Elk Grove Blvd, Elk Grove, CA 95624

Activity Timeline

Storm damage occurred

Nov 20, 2025 at 2:00 AM

Atmospheric river brought 3.2 inches of rain and 45 mph gusts overnight. Tarps covering lumber yard failed. Approximately 8,000 board feet of lumber and 200 sheets of drywall damaged.

Damage assessed & claim filed

Nov 21, 2025 at 8:00 AM

Warehouse team assessed damage. Photos and material inventory submitted with claim. Estimated loss: $12,400.

Adjuster inspection

Nov 25, 2025 at 2:00 PM

Karen Liu inspected warehouse site. Confirmed extent of water damage to materials. Noted tarps were inadequate for storm severity.

Claim approved

Dec 2, 2025 at 9:00 AM

Claim approved. Total covered: $12,400 less $2,500 deductible = $9,900 payout.

Payment issued

Dec 10, 2025 at 12:00 AM

Check for $9,900 issued to Pacific Ridge Builders. Deposited Dec 14.

Claim closed

Dec 15, 2025 at 12:00 AM

Materials replaced. Zurich recommended upgrading to enclosed storage. Claim closed.

Claims Adjuster

Karen Liu

Zurich North America

(847) 555-0142k.liu@zurich.com
Ref: ZNA-IM-2025-33891

Related Policy

Inland Marine / Builders Risk

Policy #: IM-2025-004321

Effective: Jun 1, 2025Jun 1, 2026

Premium: $7,200/yr

active

Key Dates

Date of LossNov 20, 2025
Claim FiledNov 21, 2025
Last ActivityDec 15, 2025
Days Open294